Why does the lowest bid often become the most expensive project?
The Strategies Behind Winning Construction Tenders

Introduction
Is it a go or a no-go? Submitting a tender at a fair price is rarely enough to win construction work. Many public works contracts go to the lowest-price, technically acceptable bid. Using the same drawings, every competitor submits an estimate and a technical approach, yet slight differences in price decide who wins. But firms do more than submit a proposal: they choose a bidding strategy that they believe will give them a competitive advantage.
Below are six selected strategies and what each is meant to achieve. Some of these are open business decisions. Others are rarely admitted, and intent is often hard to prove. A low bid followed by many change orders may be a deliberate strategy by a bidder who knows the design has gaps or flaws.
Regardless of which strategy is used, a pattern emerges within the industry. Perhaps you or your executive team have used one or more of these strategies in an effort to increase your company's win rate.
Incumbency Advantage & Familiarity Bias
Firms that have already worked for a client start every new tender with two advantages. The first is incumbency advantage. An incumbent knows the client’s sites, standards, decision-makers and how its projects really run, so it can price with less guesswork and a smaller risk margin, while a newcomer has to build the unknowns into its price. The incumbent has usually also passed prequalification, set up reporting and payment routines, and earned references with that client, so each new bid costs less to prepare. This is why many large professional-services firms make winning more work from existing clients their main goal: in one benchmark survey, proposals to existing clients succeeded 62% of the time, against 40% for proposals to new clients (1).
The second is familiarity bias on the client’s side: a known firm simply feels less risky. Where clients are free to choose, they act on that feeling. In a 2025 survey of 350 construction professionals in the US Mid-Atlantic, 53% of buyers said they have at least one vendor they never put out to bid and simply hire on trust (2). The two effects reinforce each other, because every win adds knowledge, references and trust that make the next win more likely. Still, familiarity rarely removes competition altogether. 80% of respondents said that more than half of their repeat customers still make them bid for new projects.
In public low-bid tenders, where the client cannot simply pick a firm it likes, the advantage works through price and competition instead. The incumbent can bid more accurately and often faces few rivals: on US state highway contracts, only about 2.5% of bids come from firms new to the market (3).
Auction Fever
The winner’s curse arises because no one knows exactly what a construction job will cost at the time of bidding. Every firm prices the same drawings and quantities with its own estimate: some come in too high, others too low. Even if the estimates are right on average, the contract goes to the lowest bid, which usually means it goes to the firm that underestimated costs the most. The more firms that bid, and the more uncertain the job, the wider the spread of estimates and the further off the winner is likely to be (4). For the client, this creates problems on both sides of the award. After it, a contractor that has won at a loss tries to recover the money through change orders, claims and cheaper methods, or in extreme cases walks away from the project. On Florida’s $2.3 billion I-4 Ultimate highway, the contractors went from forecasting a $255 million profit to losses of more than $500 million, and the project’s final cost came closer to $3 billion (5).
Pricing From Past Bid Data
Pricing a bid from past data feels safe because the numbers are real. But a bid tabulation is a snapshot of one market on a single day. It doesn’t show how far prices have moved since then, how location, quantity or competition shift the price, or what the work actually cost once built: for most state DOTs, final construction costs end up at 102–110% of the low bid (6), and in Maine, single-bid projects averaged 124% of the estimate against 104% where several firms competed (7). A database of winning bids is also a database of the lowest, and so most likely underpriced, bids, which means it carries yesterday’s winner’s curse into the next budget. For the owner, the error shows up on bid day, when the only options left are to find more money, cut scope, or reject the bids and rebid, and each of these costs time while prices keep moving. An out-of-date estimate also distorts how bids are judged: realistic offers look padded and underpriced ones look reasonable, which pushes the award towards the contractor who made the same mistake. The gap is common. FHWA considers an estimating process accurate when the engineer’s estimate falls within ±10% of the low bid on at least half of projects (8). In Kentucky, for example, the share of asphalt projects awarded above the engineer’s estimate rose from 29.5% in 2018 to 45.1% in 2023 (9). When markets cool, the error reverses (in a recent index covering Texas, Indiana and South Dakota, the median low bid was 89.8% of the estimate) (10), so an estimate anchored in past prices lags the market in both directions.
Loss-leader Bids
Bidding below cost on purpose looks irrational until you notice that, for some firms, the contract being bid is not the real prize. A loss-leader bid treats the first job as an entry ticket and expects the profit to come later, from follow-on work, a longer client relationship or a stronger market position. The reasons are familiar ones. A new entrant needs a first reference project, and in public work a track record with an agency often decides the next award. US procurement lawyers point out that a below-cost bid can be a way to get a “foot in the door” and build past performance with a particular agency. A firm that has lost earlier competitions may underprice rather than be shut out of a market for years. Boeing adopted a fixed-price bidding strategy after losing major development contracts, including the F-35 to Lockheed Martin and the B-21 bomber to Northrop Grumman, expecting to take a financial hit during development and make up profits later in production and sustainment (11). In a slow market, a job priced to cover only direct costs still keeps crews employed, bonding capacity active, and the company visible for future work. The goodwill it earns can also bring a stronger owner-contractor relationship or the promise of future work, which is the reciprocity the strategy depends on. The approach works only if the follow-on work actually arrives and costs stay predictable. When they don’t, the “investment” becomes a plain loss: Boeing’s $4.9 billion in 2024 charges on its fixed-price contracts were the largest loss its defense unit had ever recorded (12).
Buying The Job
Similarly, buying the job rests on a simple asymmetry: price is competitive only once, at the bid, while everything that changes afterwards is priced in a one-to-one negotiation. A contractor following this pattern reads the tender documents less as a description of the project and more as a map of where they are incomplete. Thin design, uncertain quantities, unresolved permits or ground conditions. It prices the base scope low, expecting those gaps to come back as paid changes. US federal rules call this logic “buying-in” and define it as “submitting an offer below anticipated costs, expecting to increase the contract amount after award (e.g., through unnecessary or excessively priced change orders)” (13). Research on highway procurement suggests that bidders respond “strategically to contractual incompleteness”, so the changes they expect are already built into their prices (14). Later research shows that a low total can be assembled through skewed bidding, which loads unit prices onto items that are likely to overrun (15). The contractor’s leverage grows once work starts. The owner cannot replace the contractor mid-project without delay and new costs, so every change is negotiated with a firm that knows it controls the schedule. The pattern shows up in outcomes rather than in stated intentions. California’s high-speed rail program awarded one segment to a bid $506 million below the next bidder and then approved 273 change orders that added more than $800 million, or 62 percent above the contract price (16). The strategy is a bet, not a guarantee. It works only where the contract leaves room for claims, and it can fail when the owner has placed the risk on the contractor: on Seattle’s SR 99 tunnel, a jury rejected the contractors’ $330 million in claims (17).
Unbalanced Bidding
Unbalanced bidding means keeping a bid's total price competitive while spreading that price unevenly across its line items, so that some items are priced well above their real cost and others well below. A bid is mathematically unbalanced when its lump-sum or unit prices do not reasonably reflect the actual cost of the work, plus a reasonable allowance for overhead and profit (18). It takes several forms. Front-end loading overprices work that is paid for early, such as mobilization or traffic control, so the contractor collects cash sooner. On Missouri DOT contracts, bids cluster just below MODOT’s 10% mobilization threshold (19). Back-end loading does the opposite and overprices late items, for example to hedge against prices rising later in the job. Quantity-error exploitation, or rate loading, raises the price of items the bidder expects to overrun the owner's quantities and cuts items expected to underrun, because contractors can often predict where the owner's quantities are wrong (20). Its extreme version is the token or “penny” bid on items the bidder expects to be reduced or deleted. Option loading shifts price from the base work to options or alternates that may or may not be exercised. For the owner, the main risk is that the lowest bid on paper turns out not to be the lowest final cost. A bid becomes materially unbalanced when there is reasonable doubt it will produce the lowest final cost, or when correcting a quantity error would change which bidder is lowest (18). Front-loading means the owner pays in advance for work not yet done and in effect finances the contractor, which hurts most if the contractor defaults and someone else has to finish the remaining, underpriced items. Rate loading pays off whenever the owner’s quantities are wrong, and any added work is paid at the inflated rates. Finally, unbalanced prices distort the bid history that owners use to prepare their next estimates, which links this strategy back to the problem of pricing from past data.
Closing
The six strategies described here are not all known examples. Firms also form joint ventures, offer alternative designs or compete on quality. But the strategies above are among the most common ways firms use price, information and timing to win work, and they share one feature: the price on the award sheet is rarely the whole story. For contractors, knowing them helps separate a calculated bet from a mistake repeated with confidence. For clients, it means reading bids more carefully. None of these strategies guarantees a profit, and none is a reason to distrust every low bid. Understanding them simply makes the risks that come with each job visible before the contract is signed, rather than after.
Sources:
7th Annual QorusDocs Proposal Management Benchmark Study
Sandler, The Contrarian Contractor (2025), by Matthew Neuberger
Currier, L. (2026). Competition and the Cost of U.S. Infrastructure
Bazerman, M. H., & Samuelson, W. F. (1983). “I Won the Auction But Don’t Want the Prize.”
The appeals court opinion (the main source). Lane Construction Corp. v. Skanska USA Civil Southeast, Inc., No. 24-12638 (11th Cir. Apr. 15, 2026).
Liu, Kwigizile & Huang (2022), Competitive Bidding in Construction Contracting
O’Brien, Rubin & Brown (2022), Bid Inflation for Highway and Bridge Projects: Challenges & Solutions
FHWA, Guidelines on Preparing Engineer’s Estimate, Bid Reviews and Evaluation.
Brown, R., Skinner, J., Terry, P., & Spears, W. (2024). Single-Bid Asphalt Contracts (Research Report No. 488). Kentucky Legislative Research Commission, for the Legislative Oversight and Investigations Committee. Adopted August 15, 2024.
A vendor-compiled index of official TxDOT, INDOT and SDDOT bid tabulations (ConstructionBids.ai, Q4 2026).
FlightGlobal. (2022, October). Troubled fixed-price defence contracts drive $3.3bn loss for Boeing
Breaking Defense. (2025, January). Boeing to log $1.7B in defense program losses in fourth quarter.
FAR 3.501-1, "Buying-in" (US Federal Acquisition Regulation)
Bajari, Houghton & Tadelis (2014), "Bidding for Incomplete Contracts: An Empirical Analysis of Adaptation Costs", American Economic Review, 104(4)
Luo & Takahashi (2025), "Bidding for Contracts under Uncertain Demand: Skewed Bidding and Risk Sharing", RAND Journal of Economics
Vartabedian (2021), Los Angeles Times, February 22, 2021, republished by Governing: "Once-Low-Cost Bullet Train Plan Will Now Cost $800M Extra"
The Columbian, December 16, 2019 (Seattle Times story): "Highway 99 tunnel contractor to appeal"
Florida DOT bid review procedure (No. 600-010-001, effective October 21, 2020)
Marion & Rosa (2025), "A bid strategy for earlier payment", NBER Working Paper 33606
Bolotnyy & Vasserman (2023), "Scaling Auctions as Insurance: A Case Study in Infrastructure Procurement", Econometrica, 91(4), 1205–1259